Project management exercise
Average difficulty

This Microsoft Software PROJECT MANAGEMENT exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Build 3 Walls - Levelling Using the Resource Levelling Tool

1) Download the files needed to start this exercise: exercise-291.zip (and click here if you experience any problems unzipping this file after downloading it).
2) Open the file Build3Walls.mpp.
3) View the Resource Sheet and Resource Graph to confirm that you have a conflict.
4) Switch to the Levelling Gantt view - you can find this in the More Views... option of the View menu.
5) Choose Level Resources... from the Tools menu and level the entire project on a day by day basis.
Training exercise hint It is a good idea to check Project Statistics before and after Levelling.
6) Compare the differences between the original and 'levelled' projects.
7) Close the file without saving the changes.