Exercise: Task Types - Fixed Duration Demonstration

1) Start a new project scheduled to start today.
2) Create the following task:
Exercise screen-shot 2240 A simple task with a duration of 10 days
3) Display the Task Information dialog box and set the task type to Fixed Duration.
4) Switch to the Resource Sheet and create the following work resource:
Exercise screen-shot 2241 Don't forget to set the Max Units to 200%
5) Switch back to the Gantt Chart, change the table view to Work and assign the resource @ 100%.
6) Increase the assignment to 200%.  Notice that the duration stays fixed but the work changes.
7) Experiment with changing resource assignments, work and durations, noting how Project 'balances' the formula.
8) Close the file without saving the changes.