Microsoft Software
Project tracking exercise
Average difficulty

This Microsoft Software PROJECT TRACKING exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Pyramid Tracking 8 weeks

1) Download the files needed to start this exercise: exercise-234.zip
2) If necessary switch to the Tracking Gantt view.
3) If necessary change the Table view to Tracking.
4) Update the project, marking work as complete through to today's date.
5) The fixed cost for the Site was actually £12,000.
Training exercise hint You may need to use the Cost table to update the fixed cost of a Summary Task.
6) The actual cost of laying the foundations was £80,000.
7) View some of the following reports:
  • Project Summary
  • Overbudget Tasks
  • Overbudget Resources
  • Budget
  • Slipping Tasks
8) Close the file without saving the changes.