Resources exercise
Average difficulty

This Microsoft Software RESOURCES exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Pyramid - fixed costs and resources

1) Download the files needed to start this exercise: exercise-221.zip (and click here if you experience any problems unzipping this file after downloading it).
2) Open the file called Build a Pyramid - Work Hours.mpp.
3) Change the table view to Cost and enter the following fixed cost:
  • Blocks (£250,000.00)
4) Create the following (shown in part) work resources:
Exercise screen-shot 343 Three work resources
5) Make the following assignments:
  • Quarrymen @ 2500% => Quarry stone
  • Masons @ 1000% => Prepare stone
  • Builders @ 3000% => Build
6) Notice the changes in durations.
7) Use views to review costs and durations.
8) Close the file saving the changes.