Tasks - other topics exercise
Relatively easy

This Microsoft Software TASKS - OTHER TOPICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Fixed duration tasks illustrated

1) Create a new project file scheduled from a start date.
2) Create the following fixed duration task:
Exercise screen-shot 2217 A fixed duration task with a duration of 10 days
3) Create the following Work resource (shown in part):
Exercise screen-shot 2218 A work resource representing two full time workers
4) Assign the resource @ 100%.
5) Increase the assignment to 200%.  Notice the duration does not change - but the work has!
6) Experiment changing resource assignments, work and durations, noting how Project 'balances' the formula.
Training exercise hint Discuss any unexpected results with your friendly trainer
7) Close the file without saving the changes.