Project basics exercise
Relatively easy

This Microsoft Software PROJECT BASICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: simple recruitment

1) Create a project file scheduled from a start date.
2) Switch to Gantt Chart view if necessary.
3) Ensure that the table view is set to Entry.
4) Enter the following tasks and durations:
  • Draft advert (1 day?)
  • Research publications (1 day?)
  • Place advert (7 days?)
  • Review applications (1 day?)
  • Schedule interviews (1 day?)
  • Interviews (1 day?)
  • Compile shortlist (1 day?)
  • Schedule interviews (1 day?)
  • Review (1 day?)
  • Offer post (1 day?)
5) Link all tasks together so that your Gantt chart resembles the example below:
Exercise screen-shot 2231 Notice how the tasks span across non working time
6) Save the file with the name Recruitment.mpp and close it down.