This Microsoft Project TASKS - OTHER TOPICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.
A full answer to this exercise is provided as part of the training course!
| 1) | Download the files needed to start this exercise: exercise-932.zip (and click here if you experience any problems unzipping this file after downloading it). | ||
| 2) | Open the file found in the folder shown above. | ||
| 3) | Assign the 24 hour calendar to each of the individual tasks within the project. | ||
| 4) | Make the following resource assignments, ensuring the task durations do not change.
|
||
| 5) | The overall duration of your project will now have changed back to 4.25 days, why? | ||
| 6) | Correct this to ensure the overall duration is 2 days, your final plan should look similar to the below: | ||
Amend the zoom level to see the effect in more detail.
|
|||
|
|||
| 7) | Save the updated file as Flights Planned and close it down. | ||