This Microsoft Project PROJECT BASICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.
| 1) | Download the files needed to start this exercise: exercise-290.zip (and click here if you experience any problems unzipping this file after downloading it). |
| 2) | Open the file Build a Wall.mpp, which has two Fixed Work and one Fixed Duration task: |
The build task has work hours already entered
|
|
| 3) | Create the following resource: |
Not all columns are shown here
|
|
| 4) | Notice how the work hours are calculated as you make the following assignments:
|
| 5) | Assign a single Brickie (100%) to the Build task and notice that Project automatically calculates how many Brickies are needed: |
If you now change the resource assignment Project will alter the work hours
|
|
| 6) | Close the file without saving the changes. |