Microsoft Project
Resources exercise
Harder than average exercise

This Microsoft Project RESOURCES exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Client visit - recourses and calendars

1) Download the files needed to start this exercise: exercise-226.zip (and click here if you experience any problems unzipping this file after downloading it).
2) Open the project file Client Visit.mpp, located in the folder shown above.
3) Assign the 24hr Calendar to all tasks.
Exercise screen-shot 2215 Before assigning the 24hr calendar
4) Notice the change in duration of the Summary Task.
Training exercise hint An alternative solution would be to enter Elapsed durations (which ignore calendars).  e.g. 2.5eh, 10ed, 1ewk
5) fdfdf
Exercise screen-shot 2216 After assigning the 24hr calendar
6) Assign the three work resources to all five sub-tasks.  Notice the duration does not change.
7) Close the file saving the changes.