Tasks - other topics exercise
Average difficulty

This Microsoft Project TASKS - OTHER TOPICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Client Visit

1) Create a new project file scheduled from a start date.
2) Enter the following fixed duration tasks and durations:
  • Client visit (1 day)
  • Train to Euston (2.5 hours)
  • Taxi to client (20 minutes)
  • Meeting (5 hours)
  • Taxi to Euston (20 minutes)
  • Train to Manchester (2.5 hours)
3) Group and link the tasks as shown below:
Exercise screen-shot 499 The summary task calculates the total duration.
4) Create the following resources:
Exercise screen-shot 500 We are travelling first class!
5) Save the file with the name Client Visit.mpp.