Tasks - other topics exercise
Average difficulty

This Microsoft Project TASKS - OTHER TOPICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Build a Wall

1) Create a new project file scheduled from a start date.
2) Change the table view to Work (or insert the Work column onto the Entry table) and enter the following Fixed Work tasks:
  • Build a wall (0 hours)
  • Mix mortar (0 hours)
  • Prepare ground (0 hours)
  • Build (24 hours)
3) Group the tasks as shown below:
Exercise screen-shot 2208 The summary task calculates the total work
4) Create the following links:
  • Mix mortar => Prepare ground
  • Prepare ground => Build
5) Save the file with the name Build a Wall.mpp and close it down.