This Microsoft Project TASKS - OTHER TOPICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.
| 1) | Create a new project file scheduled from a start date. | ||
| 2) | Create the following fixed work task: | ||
A fixed work task with work of 80 hours
|
|||
| 3) | Create the following Work resource (shown in part): | ||
A work resource representing two full time workers
|
|||
| 4) | Assign the resource @ 100%. | ||
| 5) | Assign the resource @ 200% - notice the change in duration. | ||
| 6) | Experiment with changing resource assignments, durations and work hours, noting how Project 'balances' the formula. | ||
|
|||
| 7) | Close the file without saving changes. | ||