Microsoft Project
Tasks - other topics exercise
Relatively easy

This Microsoft Project TASKS - OTHER TOPICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Fixed unit tasks illustrated

1) Create a new project file scheduled from a start date.
2) Create the following fixed units task:
Exercise screen-shot 2219 A fixed units task with a duration of 10 days
3) Create the following Work resource (shown in part):
Exercise screen-shot 2220 A work resource representing two full time workers
4) Assign the resource @ 100%.
5) Increase the assignment to 200% - notice the change in duration.
6) Experiment changing resource assignments, work and durations, noting how Project 'balances' the formula.
Training exercise hint Discuss any unexpected results with your friendly trainer
7) Close the file without saving the changes.

Thank you for showing an interest in this Microsoft Project training course!

All content � Wise Owl Business Solutions Ltd 2007.  All rights reserved.  Design by Branches.