Microsoft Project 2007
Calendars and Scheduling exercise
Average difficulty

This Microsoft Project 2007 CALENDARS AND SCHEDULING exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT 2007 course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.

Exercise: Summer Shutdown - Changing Working Time

A full answer to this exercise is provided as part of the training course!

1) Create a new blank project file.
2) Use the Project Information dialog box to:
  • schedule the project from a Project Start Date of 1 June this year; and
  • choose an overall project calendar of 24 Hours
3) You may notice that the Gantt Chart is still showing Nonworking Time for the Standard calendar.  Remedy this by formatting the Gantt's nonworking time with the correct calendar.
Exercise screen-shot 2200 Right-click on the Gantt Chart and choose Nonworking Time
4) The office will shut down for 2 weeks in the summer.  Use the Change Working Time dialog box to create an Exception called "Summer Shutdown" and make the first 14 days of August nonworking time.
Exercise screen-shot 2201 Exception days are marked in blue
5) Scroll through to August on the Gantt Chart to check that the summer shutdown period is correctly displayed as nonworking time.
6) Save the file with the name August Shutdown.mpp and close it down.

Thank you for showing an interest in this Microsoft Project 2007 training course! As mentioned above, full answers to this and other exercises are provided on the course. On all Wise Owl scheduled courses delegates can take away these model answers (together with their own efforts!) on a free USB stick.