This Microsoft Project 2007 PROJECT BASICS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT 2007 course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.
A full answer to this exercise is provided as part of the training course!
| 1) | Download the files needed to start this exercise: exercise-891.zip (and click here if you experience any problems unzipping this file after downloading it). | ||
| 2) | Open the file found in the folder above. | ||
| 3) | Assign the 24 hour calendar to each of the tasks within the project. | ||
| 4) | Make the following resource assignments, ensuring the task durations do not change,
|
||
| 5) | Your duration will have changed back to 4.25 days, why? | ||
| 6) | Correct this to ensure the overall duration is 2 days, your final plan should look similar to the below: | ||
Amend the zoom level to see the effect more clearly.
|
|||
|
|||
| 7) | Save the updated file as Journey Planned and close it down. | ||
Thank you for showing an interest in this Microsoft Project 2007 training course! As mentioned above, full answers to this and other exercises are provided on the course. On all Wise Owl scheduled courses delegates can take away these model answers (together with their own efforts!) on a free USB stick.
Recommended sites: C# corner | Computer tutorials | Training classes