This Microsoft Project 2007 ADVANCED TASKS exercise is provided to allow potential course delegates to assess their suitability for the Wise Owl MICROSOFT PROJECT 2007 course only, and may not be reproduced in whole or in part in any format without the prior written consent of Wise Owl.
A full answer to this exercise is provided as part of the training course!
| 1) | Download the files needed to start this exercise: exercise-888.zip (and click here if you experience any problems unzipping this file after downloading it). |
| 2) | Open the file found in the folder shown above. |
| 3) | Assign the appropriate Task Types and Effort Driven indicators as shown below: |
The Type and Effort Driven columns have been inserted to the Entry Table.
|
|
| 4) | Make the resource assignments as indicated below to create a plan similar to the below maintaining the durations as indicated: |
You can change the Max Units to Decimal via the Schedule tab on Tools => Options...
|
|
| 5) | The three escapees cannot spend 100% of their time on Dig Tunnel as they will be missed, change the assignment on this task to 25% of each of their time. How long will this task now take? |
| 6) | Save the updated file as Escape Planned and close it down. |
Thank you for showing an interest in this Microsoft Project 2007 training course! As mentioned above, full answers to this and other exercises are provided on the course. On all Wise Owl scheduled courses delegates can take away these model answers (together with their own efforts!) on a free USB stick.